Debarment affidavit washington state

MRSC logo

Have a Research Question?

Have a Research Question?

Awarding a Contract

RCW 39.04.010 requires local agencies to award public works contracts to a responsible bidder with the lowest responsive bid. This applies to informal bidding, such as a small works roster, as well as formal competitive bids.

Agencies may not negotiate with any of the bidders. Some submissions may involve errors, omissions, or other irregularities, and agencies must decide how to handle them.

What is a Responsive Bid?

Responsive bids are bids that are submitted on time with all of the information the agency requested. Agencies should identify in the bid documents an official bidding clock located in the room where the bids will be opened. This clock should be checked on a bid opening day to verify its accuracy.

Bids submitted after the submittal deadline or at the wrong location should be rejected as non-responsive – in other words, agencies should neither accept nor open late bids. If a contractor claims extenuating circumstances, refer them to your agency’s attorney.

Typically, bidders must provide the following information at the time of bidding:

While it is possible to do a brief check when the bids are first opened, the agency must reserve the right to ascertain full compliance with the bid proposal requirements after a more detailed review.

Additional items may be required shortly after bid opening:

What is a Responsible Bidder?

Responsible bidders, as defined in RCW 39.04.010 and 39.04.350, must meet a number of mandatory criteria. The bidder must:

Verifying Responsible Bidder Status

The certification that the bidder has not violated labor laws in the last three years is the only criteria that may be satisfied by a sworn statement. All other criteria must be verified by the agency, except for the ESD number which cannot be verified online and must be provided by the bidder. However, public agencies may ask bidders to submit a Bidder Information sheet to help verify these criteria.

State agencies provide several resources to verify the status of a contractor:

Also see the Mandatory Bidder Responsibility Checklist, originally developed by Mike Purdy for CPARB and updated in 2021 by MRSC, which can be used to document whether a bidder meets the mandatory responsible bidder criteria.

Supplemental Responsible Bidder Criteria

In addition, RCW 39.04.350(3) allows agencies to adopt additional relevant responsible bidder criteria for individual projects. The Capital Projects Advisory Review Board (CPARB) has developed Suggested Guidelines for Bidder Responsibility to help local and state agencies in developing these supplemental criteria. To view the most recent version, see CPARB's Background and Reference page and click on "Bidder Responsibility Guidelines."

Many local agencies have developed supplemental criteria on two levels:

These supplemental criteria and associated evaluation methods must be provided in the invitation to bid or bidding documents.

Responsible Subcontractor Criteria

RCW 39.06.020 requires a public works contractor to verify responsibility criteria for each first tier subcontractor, and a subcontractor of any tier that hires other subcontractors must verify responsibility criteria for each of its subcontractors. Verification is to include that, at the time of subcontract execution, each subcontractor meets the responsibility criteria listed above and in RCW 39.04.350(1) and additionally - if applicable - possesses an electrical contractor license, elevator contractor license, or plumbing contractor license.

This verification requirement, as well as the responsibility criteria, must be included in every public works contract and subcontract of every tier. However, agencies are not required to independently verify subcontractor responsibility or keep subcontractor records.

Notice of Award and Notice to Proceed

After all the bids are opened, the agency should identify the apparent low bidder for the record, but note that agency staff will review the bids submittals for completeness and numerical accuracy. Once this review is completed, generally within a maximum of 30-45 days, agency staff will recommend award of the contract to a responsible bidder with the lowest responsive bid. The agency must allow adequate time for bidders to submit written bid protests, as described below, before awarding the contract.

Upon approval by the agency’s governing body or designated staff person, a Notice of Award is sent to the contractor, which requires them to submit the following, typically within 10 or 20 business days after the date of the Notice:

After the contract is signed by the agency’s designated representative, the agency will issue a Notice to Proceed, usually transmitting the signed contract and stating the official time of completion of the contract based on the contract documents. Many agencies also remind the contractor that prior to any payment under the contract, the contractor must provide an approved statement of intent to pay prevailing wages from the contractor and any subcontractors that work in any given pay period.

Awarding to the second-lowest bidder: Certain local governments, if authorized by statute, may award public works contracts to the second-lowest responsible bidder submitting a responsive bid if both of the following conditions are met:

For the agency-specific statutes, see:

Any second class city, code city, or town that awards a contract to the second-lowest responsible bidder under those criteria must make an annual report to the state Department of Commerce including the total number of bids awarded to certified minority or women contractors and describing how notice was provided to potential certified minority or women contractors. See RCW 35.23.352(14). It does not appear that this requirement applies to any of the other local government types listed above.

Bid Protests

Agencies should anticipate bid protests and have procedures in place for handling them. For all competitively bid projects, the awarding agency, within two business days of the bid opening, must provide copies of the bids it received if requested by a bidder (RCW 39.04.105).

The agency may not award the contract during this two-day window, and if bid copies are requested by a bidder, the agency must wait at least two full business days after providing copies before awarding the contract. (A “business day” does not include intermediate Saturdays, Sundays, or legal holidays.)

If a written protest is submitted within (a) two full business days following the bid opening, or (b) two full business days following when the municipality provided copies of the bids to those bidders requesting them, the agency may not execute a contract for the project with anyone other than the protesting bidder without first providing at least two full business days’ written notice of its intent to execute a contract for the project.

Practice Tip: To implement the statutory bid protest requirement, an agency may wish to consider a policy similar to this:

  1. Only bidders that submitted a bid, subcontractors, or others that can show substantial economic interest in the bid award and who are aggrieved, are eligible to protest. After bid opening, protests are limited to issues related to bid opening, evaluation of bids, and intention to award decisions, and are further limited to those items that were not known or could not have been reasonably known prior to bid opening.
  2. Within 2 full business days (the equivalent of 16 business hours) after the advertised date and time of bid opening, as amended (Saturday, Sunday, and legal holidays excluded), any party planning to protest must file written notice of such intention with the official named in the bid document for that purpose. If no notice is received by that official within the 2 business days, all eligible protesters will be considered to have waived their right to protest. Notice of intention must stipulate (1) name, address, and phone number of the aggrieved person; (2) the bid number and title for under which the protest is submitted; (3) the grounds for protest.
  3. After the two business days have passed from bid opening date/time, the agency will proceed as follows.
  1. If a notice of intent to protest was filed with the City during the 2 days following bid opening, the City may, in the City’s determination, suspend the award decision to allow consideration of the protest before award is made; or declare its intent to award and wait a minimum of 16 business hours (2 business days as defined above) before entering into a contract. Written notice of intent to execute a contract shall be met by either one of the following methods:
    1. Public posting by the City with a named intent to award indicated on the posted tabulation, made public or accessible to the public by telephone and/or posting on the City internet location designated for bid results; or
    2. A City Council memorandum request to authorize award to the apparent successful bidder. The first memorandum request that is submitted to Council for work session consideration shall be considered notice of intention to award.

    Proof of Insurance

    Every agency must require proof of insurance coverage from all contractors and subcontractors via endorsements naming the agency as additionally insured on those policies for all projects, regardless of dollar size. Each agency should review potential risks for each project with its risk manager and/or insurance carrier.

    If your agency does not have standard insurance requirements, you may use Section 1-07.18 of the Local Agency General Special Provisions (GSPs) regarding Public Liability and Property Damage Insurance. There are several other GSPs regarding insurance that an agency may want to consider using depending on the size and complexity of the project.

    Examples of Public Works Bid Documents

    Below are selected examples of public works bidding and award documents.

    Templates and Supplemental Bidder Responsibility Criteria

    Note that these may not reflect the new bidder responsibility criteria and requirements that took effect between 2017 and 2019, as described above. We are in the process of seeking more recent documents that comply with the new legislation.

    Asbestos/Hazardous Materials Abatement

    Building Demolition

    Tree Trimming & Removal

    Additional Public Works Bid Documents

    We will be adding more examples in coming months; for additional sample documents regarding purchasing and contracting, you can search or browse MRSC's Sample Document Library: RFP/RFQ/Bid Documents.